RealEZ Notes

Phase 1

Timeline

Two shapes, same foundations-first discipline in both: QA starts month 1, CI/CD and IaC are a required week-1 deliverable. The real difference is duration and scope, not process.

gantt
    title Full Pilot (6 months)
    dateFormat  YYYY-MM-DD
    axisFormat  M%-m
    section Foundation & Scaffolding
    CI-CD, IaC, security baseline  :a1, 2026-01-01, 20d
    App scaffolding, all 5 portals :a1s, 2026-01-01, 25d
    QA starts immediately, not month 3      :a1b, 2026-01-01, 60d
    Auth, multi-tenancy, AWS prod            :a1c, 2026-01-01, 60d
    E-signature engine (in-house) begins     :a2, 2026-01-15, 90d
    Jurisdiction rules design (2-3 states)   :a3, 2026-01-01, 60d
    Transitional Document POC                :a1p, 2026-01-15, 45d
    Merchant Integration POC                 :a1q, 2026-01-15, 45d
    Hiring ramp (4 FTE hires; Designer engaged project-based) :a4, 2026-01-01, 30d
    section Build
    E-sig legal review                       :a5, after a2, 45d
    Jurisdiction rules + forms built         :a6, after a3, 60d
    Escrow-partner sandbox integration       :a7, 2026-03-01, 60d
    Transitional Document feature-complete   :a8a, after a1p, 60d
    Merchant Integration feature-complete    :a8b, after a1q, 60d
    Native mobile build, all 5 portals       :a9, 2026-03-01, 60d
    section Harden & Launch
    Pen test and remediation                 :a10, 2026-05-01, 30d
    Counsel sign-off                         :a11, 2026-05-01, 30d
    App store submission                     :a12, 2026-05-15, 30d
    Pilot onboarding                         :a13, 2026-06-01, 30d
        
gantt
    title Lean Pilot (5 months)
    dateFormat  YYYY-MM-DD
    axisFormat  M%-m
    section Foundation & Scaffolding
    Tech lead + Technical PM + HR/Admin join :b0, 2026-01-01, 20d
    CI-CD, IaC, security baseline   :b1, 2026-01-01, 20d
    App scaffolding, all 5 portals  :b1s, 2026-01-01, 25d
    QA starts immediately, not month 2        :b1b, 2026-01-01, 30d
    Auth + multi-tenancy + AWS       :b1c, 2026-01-01, 30d
    E-sig vendor sandbox wired up             :b2, 2026-01-01, 30d
    Jurisdiction rules (1 state) design       :b3, 2026-01-01, 30d
    Transitional Document POC                 :b1p, 2026-01-10, 25d
    Merchant Integration POC                  :b1q, 2026-01-10, 25d
    QA lands; Designer engaged                :b4, 2026-01-01, 30d
    section Core Build
    Transitional Document feature-complete    :b5, after b1p, 45d
    Merchant Integration feature-complete     :b6, after b1q, 45d
    E-sig wired into transaction flow         :b7, 2026-02-01, 30d
    Native mobile build, all 5 portals        :b8, 2026-02-01, 60d
    QA automation (continuous from month 1)   :b9, 2026-01-01, 120d
    section Test & Polish
    Regression + pen test                     :b10, 2026-04-01, 30d
    App store submission                      :b11, 2026-04-01, 30d
    UX polish pass                            :b12, 2026-05-01, 30d
    Go/no-go                        :b13, 2026-05-20, 11d